Breyer Group – Phase 1, 2 and 3 – January 11th Update
Phase 1 Roof parapet works are in progress and will work its way around toward phase 2., Cladding install is progressing. Internal fire collars will need to be fitted around drainage pipes within the wall in selected properties. This is due to the pipes going into the...
Breyer Group – Phase 1, 2 and 3 – December 13th Update
Please be aware that the site will be closed between Friday 23rd December 2022 and Tuesday 3rd January 2023. There will be no Breyer operatives on site or on the scaffolding during this time. Please remember that no members of the public are allowed on the scaffolding...
Breyer Group – Phase 1, 2 and 3 – December 5th Update
Phase 1 Cladding back ground ongoing to main facades. Fire barriers and cladding brackets are also progressing on concrete slab areas. The new cladding panels have now arrived on site for both the main facades of the building and the balcony walls. These will soon...