Breyer Group – Phase 1, 2 and 3 – April 25th Update

25 April 2023

Site will be closed on Monday 1st May, Monday 8th May and Monday 29th May bank holidays. Should you have an emergency directly related to the cladding replacement works during this time, please call 0800 389 9706 or email: [email protected]

All other general enquiries not related to the cladding replacement works should be directed to the Concierge or MIH building management in the usual way.

Phase 1- Some scaffolding has been removed from the top level of the block on the Webber Street side. Balcony surface insulation and tiles are currently being laid on the top two floors of the block working their way to the lower levels. The majority of the new Cladding has now been installed across Phase 1. Both types of new Cladding can be seen in the above picture.

Phase 2- Cladding has started being fitted to the upper floors on the Southwark Bridge Road side of the block and this will work its way to the lower floors over the coming weeks.

Phase 3- Fitting insulation and other Cladding back-round works are in progress around the courtyard, with new Parapets also being installed around the roof edge.