Breyer Group – Phase 1, 2 & 3 – November 20th Update

20 November 2023

As a reminder, new balcony lights and painting of balcony hand – rails are being carried out by the Mybase company separate to Breyer Group works. Those works will be arranged by the concierge.

Scaffolding has now been removed from the majority of Webber St and is down to the 2nd floor on Great Suffolk St.

Southwark Bridge Road – The Aluminium silver cladding has been installed down to the 1st floor and the balcony cladding/ walls are fitted down to 2nd floor on the Southwark Bridge Rd side of the block. Balcony water proofing, insulation and floor tiles are in progress across phase 2. Scaffolding has been removed down to level 2.

Courtyard – Insulation has been fitted throughout most floors and cladding has been installed on levels 7 and 6 and around the inner courtyard area that faces the communal corridors. Balcony water proofing has been completed down to the lower floors of the courtyard and scaffolding has been removed from level 7. The scaffolding has been removed from the top 3 levels of the inner courtyard- the mostly glazed area and the remainder of this scaffolding will be brought down first to allow extra light into the corridors and flats.