Phase 1 – Scaffolding has been removed down to level 1 of the block on the Webber St side. Balcony surface insulation and tiles have been laid to most balconies across phase 1.
Phase 2 – Cladding has started being fitted to the top 3 floors on the Southwark Bridge Rd side of the block. Balcony water proofing has reached the lower levels. Balcony insulation and tiles have been completed down to level 5.
Phase 3 – Cladding back-round works are in progress around the courtyard. Insulation has been fitted throughout most floors of the courtyard. Cladding has been installed on level 7. Balcony water proofing has started on the top levels.
Please note: There will be no Saturday working for the next 2 weeks due to rail strikes.