Breyer Group – Phase 1, 2 and 3 – December 5th Update

5 December 2022

Phase 1

Cladding back ground ongoing to main facades. Fire barriers and cladding brackets are also progressing on concrete slab areas. The new cladding panels have now arrived on site for both the main facades of the building and the balcony walls. These will soon start to be installed from the 7th floor of the building, working down toward the ground floor.

Phase 2

Cladding back-round and construction of the new “upstands” on the balcony edge is ongoing across this phase. Balcony water proofing is also ongoing across the phase.

Phase 3

Balcony waterproofing works are taking place in the courtyard during this week. As previously mentioned, this creates a strong smell, so if you are leaving your home, we would advise you to close windows and trickle vents to minimize the smell that enters the building.

Sheathing board installation is ongoing across this phase.