Breyer Group – Phase 1, 2 and 3 – April 25th Update
Site will be closed on Monday 1st May, Monday 8th May and Monday 29th May bank holidays. Should you have an emergency directly related to the cladding replacement works during this time, please call 0800 389 9706 or email: [email protected] All other general...
Breyer Group – Phase 1, 2 and 3 – March 13th Update
Phase 1 Façade cladding panels are being installed throughout all levels of phase 1. Balcony water proofing and insulation is making good progress. Phase 2 Cladding back round works and water proofing works are ongoing across this phase. Some new cladding panels have...
Breyer Group – Phase 1, 2 and 3 – March 6th Update
Phase 1 Façade cladding panels are being installed throughout the upper levels of phase 1, as shown in the attached picture of newly installed “Hardie Plank” which are a better finish than previously, due to them being close fitted, protecting the insulation behind...