Breyer Group – Phase 1, 2 and 3 – June 20th Update

21 June 2023

Please be aware that operatives will be working in the area around the main lift shafts for the next few days on all floors. Please use caution when exiting the lifts and approaching the lifts around the corners of the corridors.

Phase 1 – Scaffolding has been removed down to level 3 of the block on the Webber St side. Balcony surface insulation and tiles have been laid as far as level 3 of the block working their way to the lower levels. New Cladding has now been installed across phase 1 as shown in the photo.

Phase 2 – Cladding has started being fitted to the top 4 floors on the Southwark Bridge Rd side of the block. Balcony surface insulation and tiles have been laid on levels 7& 6. Balcony water proofing has reached the lower levels.

Phase 3 – fitting insulation and other cladding back-round works are in progress around the courtyard, with new Parapets also being installed around the roof edge. Internal vent works have now reached the mid-floors of courtyard facing properties. When you receive your start date letter, please try to be available or contact us to arrange an alternative date.