Breyer Group – Phase 1 – June 20th Update
Phase 2 scaffolding is now fully completed, inspected and handed over to the Operational Team ready for works to begin. External surveys are currently ongoing. Balcony Door Locking on Phase 2 was undertaken last week, we would like to extend our thanks to all...
Breyer Group – Phase 1 – June 7th Update
The Great Suffolk Street Elevation is now being stripped of the existing CP Board, please see image attached. Webber Street Elevation – Ongoing liquid plastic coating application to balcony upstands. Please note this work can only be undertaken in dry weather...
Breyer Group – Phase 1 – May 25th Update
Balcony works are ongoing on Phase 1, upstands at the front of balconies are currently being constructed and coated with a liquid plastic water proof system. Once complete, each balcony will be re-visited for a second application of the coating. Scaffolding on Phase 2...