Breyer Group – Phase 1 – May 9th Update

Breyer Group – Phase 1 – May 9th Update

The main facade for Phase 1 has now had all of the exisiting Cladding System removed including the majority of balcony areas. Water proofing works and CP board installation has started and a number of balconies have had the liquid plastic water proofing system...
Breyer Group – Phase 1 – April 28th Update

Breyer Group – Phase 1 – April 28th Update

We have issued all residents and leaseholders a letter advising on changes to our works programme. This will arrive via post or email depent on your choice of correspondance. The scaffold gantry is almost complete on Southwark Bridge Road. Hoarding will be installed...
Breyer Group – Phase 1 – April 25th Update

Breyer Group – Phase 1 – April 25th Update

The 1st floor gantry scaffold is in progress along Southwark Bridge Road. Following a review of the pilot area by the Design Team, we are continuing to strip the cladding and balconies on the Webber Street elevation. Balcony light disconnections are scheduled to take...
Breyer Group – Phase 1 – April 14th Update

Breyer Group – Phase 1 – April 14th Update

The scaffolding on Phase 1 is now complete and the gantry to 1st floor level of Phase 2 is in progress. Cladding removal and balcony stripping on Phase 1 is underway. We have had further enquires regarding the necessity of preventing access to residents balconies. The...