Breyer Group – Phase 1, 2 & 3 – October 26th Update
A letter has recently been issued by MIH to all leaseholders giving information on an updated programme and time frame, so look out for that if you have not received it yet. Also, new balcony lights and painting of balcony hand- rails are being carried out by the...
Breyer Group – Phase 1, 2 & 3 – September 26th Update
Phase 1 – Scaffolding has been removed along half of the Webber St elevation and is down to the first level of the block in other areas and level 3 on the Great Suffolk St side. Phase 2 – The Aluminium silver cladding has been installed down to the...
Breyer Group – Phase 1, 2 & 3 – September 4th Update
Saturday working- from 9AM until 2PM will begin again from Saturday 9thSeptember. Phase 1 – Scaffolding has been removed down to level 1 of the block on the Webber St side and level 3 on the Great Suffolk St side. Phase 2 – The Aluminium silver cladding...