Work Phasing Plan

9 February 2022

Phase 1

Webber Street 7th February 2022 – 11th January 2023 48 weeks

Great Suffolk Street 27th April 2022 – 3rd March 2023 44 weeks


Phase 2

Southwark Bridge Road 21st June 2022 – 5th May 2023 45 weeks

Belverdere Buildings 25th July 2022 – 3rd February 2023 27 weeks


Phase 3

Courtyard 8th August 2022 – 23rd August 2023 54 weeks

The reason for this sectional approach to is to strike scaffolding to each section as quickly as possible in order to minimise disruption.