Work Phasing Plan
Each Phase of Works is proposed to have a sectional completion.
Phase 3
Courtyard 8th August 2022 – 23rd August 2023 54 weeks
The reason for this sectional approach to is to strike scaffolding to each section as quickly as possible in order to minimise disruption.