Phase 2 – Work Phasing Plan

22 February 2022

Work Phasing Plan

Each Phase of Works is proposed to have a sectional completion.

Phase 2

Southwark Bridge Road 21st June 2022 – 5th May 2023 45 weeks

Belverdere Buildings 25th July 2022 – 3rd February 2023 27 weeks