Phase 1 – Work Phasing Plan

22 February 2022

Work Phasing Plan

Each Phase of Works is proposed to have a sectional completion.

Phase 1

Webber Street 7th February 2022 – 11th January 2023 48 weeks

Great Suffolk Street 27th April 2022 – 3rd March 2023 44 weeks