Breyer Group – Phase 1, 2 and 3 – March 6th Update

6 March 2023

Phase 1

Façade cladding panels are being installed throughout the upper levels of phase 1, as shown in the attached picture of newly installed “Hardie Plank” which are a better finish than previously, due to them being close fitted, protecting the insulation behind them. Balcony water proofing is making good progress. Some work has started to remove the top level of scaffolding from phase 1 in early March.

Phase 2

Cladding back round works and water proofing works are ongoing across this phase. Some new cladding panels have begun to be fitted.

Phase 3

Cladding back round works are in progress on this phase.