Phase 1 – Scaffolding has been removed along half of the Webber St elevation and is down to the first level of the block in other areas and level 3 on the Great Suffolk St side.
Phase 2 – The Aluminium silver cladding has been installed down to the 1st floor and the balcony cladding/ walls are fitted down to 3rd floor on the Southwark Bridge Rd side of the block. Balcony water proofing has reached the lower levels. Balcony insulation and tiles have been completed down to level 4. Scaffolding has been removed down to level 3 along to the mid-point on Southwark Bridge Rd.
Phase 3 – Cladding back-round works are in progress on lower levels around the courtyard. Insulation has been fitted throughout most floors and cladding has been installed on levels 7 and 6.. Balcony water proofing is being done through the mid- floors of the courtyard and some scaffolding has been removed from level 7.