Breyer Group – Phase 1, 2 & 3 – July 19th Update

20 July 2023

Phase 1 – Scaffolding has been removed down to level 3 of the block on the Webber St side. Balcony surface insulation and tiles have been laid as far as level 2 of the block working their way to the lower levels. Water proofing is in progress and will shortly be starting on Level 1 on this phase.

Phase 2 – Cladding has started being fitted to the top 3 floors on the Southwark Bridge Rd side of the block. Balcony surface insulation has been laid down to level 4. Balcony water proofing has reached the lower levels.

Phase 3 – Cladding back-round works are in progress around the courtyard. Insulation has been fitted throughout most floors now, as seen in the attached photo. Cladding has been installed on level 7.