Breyer Group – Phase 1, 2 and 3 – June 14th Update

14 June 2023

Phase 1- Scaffolding has been removed down to level 4 of the block on the Webber St side. Balcony surface insulation and tiles have been laid as far as level 3 of the block working their way to the lower levels. New Cladding has now been installed across phase 1 as shown in the photo.

Phase 2- Cladding has started being fitted to the top 4 floors on the Southwark Bridge Rd side of the block and balcony water proofing on the lower levels. Balcony surface insulation and tiles have been laid on the top floor.

Phase 3- fitting insulation and other cladding back-round works are in progress around the courtyard, with new Parapets also being installed around the roof edge. Internal vent works have now reached the upper floors of courtyard facing properties. When you receive your start date letter, please try to be available or contact us to arrange an alternative date.