Phase 1
Façade cladding panels are being installed throughout all levels of phase 1. Balcony water proofing and insulation is making good progress.
Phase 2
Cladding back round works and water proofing works are ongoing across this phase. Some new cladding panels have begun to be fitted and large areas of insulation have been installed through this phase, as shown in the attached picture.
Phase 3
Cladding back round works, including fitting of insulation are in progress on this phase.