Phase 1
Roof parapet works are in progress and will work its way around toward phase 2., Cladding install is progressing.
Internal fire collars will need to be fitted around drainage pipes within the wall in selected properties. This is due to the pipes going into the building through the fire barriers and then running through internal boxing, or in some cases- running above ceilings. If you home is one of the properties that has a pipe running internally, we will contact you individually to arrange for this to be done.
Phase 2
Cladding back round works are ongoing, roof parapets works will begin on phase 2 as they move around from phase 1.
Phase 3
Currently being surveyed for cladding back round installation, CP board changes are continuing across the phase.