Breyer Group – Phase 1, 2 & 3 – August 1st Update

2 August 2023

Please Note: Beginning from 5th August- the site will be open on Saturdays from 9AM- 2PM.

This will be for a number of weeks to allow extra progress to be made and is in-line with working hours allowed by Southwark Borough Council. The works will be external only, no internal works will be done during this time and no access to resident’s properties will be needed.

Below is a summery of the current situation of the work in each phase.

Phase 1 – (including Webber St and Great Suffolk St facing properties) Scaffolding has been removed down to level 3 of the block on the Webber St side. Balcony surface insulation and tiles have been laid as far as level 2 of the block working their way to the lower levels. Balcony water proofing is in progress and will shortly be starting on Level 1 on this phase.

Phase 2 – (Including Southwark Bridge Road facing properties) Cladding has started being fitted to the top 3 floors on the Southwark Bridge Rd side of the block. Balcony surface insulation has been laid down to level 4. Balcony water proofing has reached the lower levels.

Phase 3 – Cladding back-round works are in progress around the courtyard. Insulation has been fitted throughout most floors now and cladding has been installed on level 7.

Phase 1 property owners have recently been emailed a form directly from our easy bop system and we request that you take a few moments to complete the form and send it back over the next couple of weeks. Please remember to sign the form and ensure it is showing the correct property address before sending it. Many thanks.

Internal vent works have now reached the middle levels of the courtyard. Once you receive the letter giving the start date for the works, please try to be available to give access or contact us to arrange an alternative date.

Thank you for your patience and ongoing cooperation with the works.